Product Fitting Instructions
Tank/Liner Connector
Tank Fitting Instructions
-
Mark Tank for drilling using loose flange.
-
Drill screw holes in tank using 6.5mm or ¼" drill.
-
Cut out centre hole allowing clearance for pipe size.
-
Apply 2 x 6mm - ¼" wide annular beads of sealant one inside, one outside of screw holes in socket flange.
-
Fit to tank, aligning screw holes.
-
Align loose flange, fit screws, and tighten. (Do Not Overtighten)
-
Clean off excess sealant.
Liner Fitting Instructions
-
Mark liner using loose flange.
-
Pierce liner for screw holes using bradawl or similar.
-
Apply 2 x 6mm wide beads of sealant on one inside, one outside of screw holes in socket flange.
-
Fit to liner aligning screw holes with piercing in liner.
-
Align loose flange, fit screws, and tighten. (Do Not Overtighten)
-
Cut out pipe hole using a sharp knife.
-
Clean off excess sealant.
Dual Purpose ( Bottom Drain & Mid-Water Feed
Please Note: If used as a Mid-Water Feed, the Cover must only be used as a "push-on".
When used with a Bottom Drain the retaining screws must be used.
Instructions
-
Using a 5mm drill bit, drill only 2 holes (opposite each other) in the drill mark recess(es).
For 75mm, 90mm, 82mm and 3" use Inner Drilling Marks (in dark blue)
For 110mm and 4" use Outer Drilling Marks (in light blue)
90 Degree Bottom Drain
Please Note: If used as a Mid-Water Feed, the Cover must only be used as a "push-on".
When used with a Bottom Drain the retaining screws must be used.
Instructions
-
Using a 5mm drill bit, drill only 2 holes (opposite each other) in the drill mark recess(es).
For 75mm, 90mm, 82mm and 3" use Inner Drilling Marks (in dark blue)
For 110mm and 4" use Outer Drilling Marks (in light blue)
Directional Pond Return (DPR)
Fittings Instructions
-
Cut off the smaller socket with a fine tooth saw.
-
(using the DPR flange as a guide, if a larger pipe size is to be used.
-
Chamfer inside the edge of the larger socket for ease of pipe entry.
-
Dry fit length of pipe to DPT, minimum 1.5 times the thickness of pond wall.
-
Fit DPR in the required position, ie Height, direction, and angle. Build a wall around the pipe, leaving ample space to remove and re-fit.
-
Remove the drain pipe, glue up the joint, and re-fit when necessary.
-
If glass-reinforced plastic (GRP) is used to seal the pond, treat the DPR with Microseal T20 to effect a better bond to the GRP
-
If using a pond liner treat the DPR as a tank liner connector, as the DPR screw bosses are blind. No problems will occur with mortar ingress into the screw holes from the back of the DPR.
Cut Here
Inline Venturi - 50mm
-
Mount complete RTF Inline Venturi in pipework between pump & pond (after U.V if fitted)
-
Unscrew threaded unions and remove Venturi Body.
-
Remove both funnels from the rear of the Venturi Body, and re-fit the desired funnel.
-
Fit Air Intake Tube onto Air Feed Pipe
-
Re-fit the Venturi Body onto pipework.
-
Start the pump, and check air is being pulled into the system.
-
Try alternate funnel to obtain the best results.
IMPORTANT
The free end of the Air Intake must be kept above water level (an extension tube can be supplied).
Venturi MUST be fitted close to pipework exit into pond.
Dry fit pipework before testing, if necessary temporarily tape joints.
Try not to fit bends between Venturi and exit in pond.
Depending on pipework design, pipe run and depth of use, use small funnel up to 1000 gallons per hour, use large funnel 1000 to 2000 gallons per hour.